Nigeria’s Mega-Refinery Opens to Skepticism Seven Years Late

Aliko Dangote, Africa’s richest person, announced the opening of a mega refinery in Nigeria — seven years late — to a backdrop of skepticism about how fast it will really be able to ramp up.

(Bloomberg) — Aliko Dangote, Africa’s richest person, announced the opening of a mega refinery in Nigeria — seven years late — to a backdrop of skepticism about how fast it will really be able to ramp up.

Nigerian President Muhammadu Buhari, who leaves office later this month after serving two four-year terms, performed a commissioning ceremony at the refinery, which is near Lagos. The plant is 20% owned by Nigeria National Petroleum Co., the state oil company.

Dangote said the facility is aiming to satisfy the country’s domestic fuel demand by the end of this year. He didn’t immediately specify if he meant all the nation’s consumption. Were that to be the case, it would mean replacing millions of barrels of fuel supply and require a huge ramp-up. The plant will ship its first oil products by July or August, he said.

Despite the bullish comments, traders of West African oil said they’ve seen no commercial activity to suggest a major ramp up is at hand — either in terms of crude procurement or the hiring of traders to handle sales of finished fuels. Researchers, speaking before the ceremony, said they don’t expect any significant boost to fuel supply in the next few months.

“We view the upcoming commissioning as a symbolic gesture marking the end of Buhari’s term in office,” said Ronan Hodgson, an analyst at Facts Global Energy. “We continue to expect the Dangote refinery will not be producing anything meaningful for at least six months post-inauguration and, more likely, in the first quarter of 2024.”

READ: Nigeria’s Dangote Oil Refinery Set to Be Commissioned May 22

Despite being Africa’s top oil producer, Nigeria’s state-owned refineries are in disrepair. That’s put the country at the mercy of local and international traders who deliver products like gasoline and diesel to the country in return for crude. When it fires up fully, Dangote should help to ease or even eliminate that dependence.

So-called commissioning is the first phase of getting a refinery up and running, involving the careful processing of relatively small batches of crude. From there, full ramp-up often takes months.

NNPC said it will fulfill its supply obligations to the refinery without elaborating.

Mega Project

The $20.5 billion refinery and fertilizer mega-project is designed to have a processing capacity of 650,000 barrels a day when it’s fully up and running, far exceeding any other plant in the continent. 

The NNPC has swap arrangements through which it trades at least 330,000 barrels of crude per day for gasoline. In some recent months, that figure has topped 450,000 barrels a day. When up and running, Dangote’s facility could go a long way to curtailing that reliance.

When a $3.3 billion loan for the refinery was agreed in 2013, the aim was to have it completed in 2016. In practice, construction didn’t even begin until 2017.

Petroleum products imports cost Nigeria $26 billion in 2022 and the refinery will help eliminate the cost, Godwin Emefiele, governor of Nigeria’s central bank, said at the ceremony.

At full capacity, Dangote could yield as much as 250,000 barrels a day of gasoline as well as around 100,000 barrels a day of of gasoil and diesel, FGE estimates.

Even so, with domestic gasoline output rising, fiscal savings from lower fuel imports may be limited because crude export revenues will be reduced at the same time, according to a report by the International Monetary Fund earlier this year. The IMF’s report assumed a slow ramp-up from 100,000 barrels a day 2024 and 200,000 in 2025, noting an upside risk in the medium term if this was achieved more rapidly.

Traders said the country’s crude exports may fall once the refinery is working because it will take a substantial proportion of Nigerian supply. The nation’s oil production averaged almost 1.4 million barrels a day so far this year, according to data compiled by Bloomberg.

Dangote refinery has a deal with NNPC, which will supply around 300,000 barrels a day of crude when the refinery is up and running. That’s expected to include mostly medium-sweet, distillate-rich crude as well as lighter varieties, according to Energy Aspects Ltd., a consultant.

The plant is expected to conduct a staggered start-up of secondary units through the second half of next year and into 2025, said Randy Hurburun, a senior refining analyst at the firm. Commissioning will continue for the rest of the year, followed by an operational startup in early 2024 at between 50%-70% of capacity, he said.

“We are not seeing any indication that the refinery is securing any oil to get operations underway,” he said.

–With assistance from Anthony Osae-Brown and William Clowes.

(Updates with information about fuel swap, imports in 10th paragraph.)